|
|
Former
Vangas Facility Phase II ESA, Fairbanks, Alaska
NORTECH continued to help Suburban Propane
with their deliberative process of assessing, getting ADEC work plan
approval, then cleaning up and relinquishing their leased property back
to the ARRC by removing/disposing of a hazardous materials drum, installing
three MWs and performing soil and water sampling to assess several locations
on or adjacent to the lease lot, and then doing a Phase II report to
identify what soil remediation work had be done to satisfy the Alaska
Dept. of Environmental Conservation and the ARRC.
Block
2 Contamination Delineation - Phase II ESA, Fairbanks, Alaska
NORTECH
performed a Phase I as well as a limited Phase II ESA
for the Blocks 2 & 3 area of downtown Fairbanks in 2001. The initial
Phase II ESA effort allowed for some hazardous materials surveying of
several of the property’s existing buildings, and uncovered the presence
of TCE and other volatile organic contaminants in the site’s groundwater.
Liability concerns relative to anticipated land purchases by the City
warranted further, more detailed, investigation and delineation of the
contamination. The City of Fairbanks hired NORTECH
to perform a soil gas survey and groundwater investigation to assess
and delineate soil and groundwater contamination in the Block 2 area.
Block 2 was canvassed for property access and previous environmental
reports were reviewed for historical information in planning the soil
gas and monitoring well installation program. NORTECH's
contamination investigation pinpointed the likely source for TCE contamination,
found other localized areas of source contamination, and revealed that
aging, underground wood-stave sewer pipes were conveying and leaking
contamination under the City’s right-of-way. The results of this investigation
assisted the Alaska Department of Environmental Conservation with their
area groundwater investigation toward identifying responsible parties
and mitigating future property transfer liabilities.
UAF
Toolik Lake Diesel Spill Emergency Response, Corrective Action &
Closure – Toolik Lake,
Alaska
Risk
Management at the University of Alaska Fairbanks (UAF) requested NORTECH
assist with spill response, assessment, and cleanup of a generator diesel
spill at the Toolik Field Station (TFS) in Fall 2001. Stakeholders included
UAF, the federal Bureau of Land Management, National Science Foundation,
and others. UAF and the Alaska Department of Environmental Conservation
(ADEC) approved a corrective action plan consisting of assessment, excavation
and stockpiling of contaminated soil, and replacement with clean backfill.
Due to the significant environmental sensitivity of the research site,
UAF requested a corrective action goal of Non-Detect when removing diesel-contaminated
soils, well below the ADEC's Arctic Zone cleanup criteria of 200 mg/kg.
The remote nature of this arctic field station proved environmentally
and logistically challenging. Over 2,200 cubic yards of contaminated
soil were excavated over a 17,000 square-foot area, and stockpiled in
a lined containment cell for future remediation. Complete removal and
relocation of the TFS power generation facility and support equipment
was necessary during the project. Remote coordination with ADEC, the
analytical laboratory, and the University was integral to the completion
of the cleanup excavations, confirmation sampling, and backfill efforts.
Response fieldwork was completed in less than 30 days, well within University
expectations, and before winter closed out further operations. (2001-2002)
Phase
II Environmental Investigations
The NORTECH Team has performed several dozen
Phase II ESAs, some of which have stemmed from earlier Phase I projects,
and others which cropped up because of an identified need to more completely
assess and evaluate the contaminated condition of a property. In accomplishing
this work we have a full complement of site characterization field sampling
equipment and hardware available to complete all anticipated site characterization
requirements; including ppm and ppb photo-ionization VOC detectors,
multiple gas specific meters with interchangeable sensors for a majority
of contaminates, Indoor Air Quality (IAQ) parameters (CO, CO2, temp
and relative humidity) combustible gas meters, pressure gauges, turbidity,
Hanby kits, radiation detectors, x-ray fluorescence lead in paint, soils
and air, real time and passive monitors, physical parameters instrumentation,
site surveying and field GIS equipment, pH, conductivity, flow, water
level, and water surface and sub-surface hand and electric sampling
equipment. Available equipment includes some backup and duplicate equipment
capability in Fairbanks, Anchorage and Juneau.
HOME
| ABOUT | SERVICES
| CLIENTS | EXPERIENCE
| PERSONNEL
| EVENTS | RESOURCES
| EMPLOYMENT | LINKS
CONTACT |
SEARCH | SITEMAP
|